JOKOWI'S MEGA PROJECT IN THE MIDST OF ECONOMIC SLOWDOWN

페이지 정보

작성자 Aditya 작성일 19-11-05 16:22 조회 2,240 댓글 0

본문

Workers assemble electricity installations on high voltage towers in the 35,000 Mega Watt electricity project in Jakarta, Tuesday, November 5, 2019. The slipping of Indonesia's economic and investment targets has made President Joko Widodo's ambitious project slow down. The megaproject, which was launched in 2015 and is planned to be completed in 5 years, is currently only realizing 3,600 Mega Watts, making the government have to reschedule the completion of the project in 2022-2023. (JakartaBizWeekly/Aditya)